You have received an RFQ for valve sealant: what to do next

How to turn a one-line sealant request into an offer that holds up when the end user checks it.

The short answer

An RFQ for valve sealant is rarely a complete specification. It usually names a product, or equivalent, and leaves out the valve, the fluid and the approval rules. Ask the end user for those details, list every requirement against your offer, and send the full set to a manufacturer's engineer before you quote.

1. What the request line usually means

Most requests for valve sealant arrive as one line. It may name a product, a pack size and a delivery date.

For many end users, the named product is the only specification they hold. The right product depends on the valve and its service.

Grease, lubricant and sealant are not one product class. They do different jobs, and the wrong one can leave a valve harder to operate or still leaking. A sealant that suits a ball valve in a gas line may be wrong for a plug valve in crude oil.

So there is no honest answer to which sealant is reliable for a valve type until the service is known. Our valve sealant buying guide gives the wider picture.

2. What to ask the end user first

These questions turn a one-line request into something a manufacturer can answer. Ask them before you quote anything.

  1. Valve type and make, size and pressure class.
  2. The product already in the valve, if known.
  3. Which part has the problem (seat, stem or plug), and what the leak or fault looks like.
  4. The fluid, its temperature and pressure range, and any water, contaminants or injected chemicals.
  5. Whether the service is sour, oxygen, food or potable water.
  6. How the injection fittings are arranged on the valve.
  7. The exact named product, and whether an alternative is allowed at all.
  8. Any approval or certificate rule from the end user or the operator.
  9. The documents needed at delivery, and how urgent the need is.

Our article on the data an engineer needs to recommend a sealant explains why each item matters.

3. Where intermediaries get caught

A common trap is a requirement that never reaches the manufacturer. A trader or contractor who does not pass the end user's rules on can be forced to redo the whole order after an audit.

Certificates are a second trap. Ask the end user's buyer whether a certificate may be re-issued or re-headed, and whether approval for one size or class covers another. Do not assume it does.

Write documentation and inspection needs into the purchase order up front. Requirements left unstated tend to become disputes later.

Guessing the product or the application can cause wrong shipments and returns. A direct line to a manufacturer's engineer helps you avoid this.

4. Approved lists and the phrase or equivalent

An operator's approved vendor list is closely held and varies by application. You often cannot look it up. Ask the end user's buyer or engineer what the list requires for this item. The route onto an operator's list is set by that operator, so ask the buyer, and the manufacturer's engineer can say what its own approval covers.

Approval to supply is a starting point. It does not show that the grade or quality suits your order, so ask the manufacturer directly.

The words or equivalent ask you to prove a match, not just claim one. Some valve makers insist on their own sealant, which can rule out any alternative. Ask the end user whether such a restriction exists.

Then make a side-by-side table. Put each stated requirement against your offer, list every deviation openly, and mark an alternative as an alternative. The article on sealant specification wording shows how requirements are usually written.

5. What to send a manufacturer

Send the whole picture in one message. An engineer can then say whether a product suits, needs a different grade, or should not be used for in-service treatment at all. Treatment in service depends on injection fittings in good condition, a valve and service that suit it, and site rules and the permit-to-work allowing it, with maker documents consulted. Some requests end in assessment, repair or replacement rather than a sealant.

  1. The end user's request line, exactly as received.
  2. The answers to the questions above, with gaps marked as unknown.
  3. Photographs of the valve nameplate and the injection fittings, if you can get them.
  4. Approval, certificate and documentation requirements, in the end user's own words.
  5. Whether alternatives are allowed, and any valve maker restriction.
  6. Delivery location and date.

Product choice and how the work is done stay with the manufacturer's engineer. You remain the point of contact for your customer. See what happens after you send a valve problem and our valve sealants page.

Common questions

Sealant RFQ questions, answered directly

How do I check that a supplier's offer matches what the client specified?

Put each stated requirement beside the offer in a table and list every deviation openly. Mark any alternative as an alternative. Ask the manufacturer's engineer to confirm the fit before you submit the offer to your customer.

What can I do if the client rejects the certificates I supplied?

Ask exactly what was not accepted, then go back to the manufacturer with the end user's own wording. Ask whether the certificate may be re-issued, and do not assume one approval covers another size or class. In the next order, state documentation needs in the purchase order up front.

Can I look up an operator's approved vendor list?

Usually not openly. The list is closely held and varies by application. Ask the end user's buyer what applies to the item, and ask the manufacturer's engineer what its own approval covers.

Is valve sealant the same as ordinary grease for high pressure gas valves?

No. Grease, lubricant and sealant do different jobs, and the wrong one can cause trouble. A choice for a gas valve depends on the fluid, pressure, temperature and valve design, so send those details to an engineer first.